about
Martyr Lt. Gen. Qassem Soleimani combined cycle power plant in Kerman
History and goals:
In order to develop the country’s power generation network, especially to supply and stabilize the voltage of the southeast network in the late seventies, a study was conducted by the Ministry of Energy and based on the plan to build a combined cycle power plant with 8 gas units with a nominal capacity of 159 megawatts per unit at the center of gravity. Kerman was approved. In this way, the first phase of the power plant project, which includes the construction of 8 gas units with a total capacity of 1272 megawatts, actually started in 2019.And through the conclusion of an agreement between the Electricity Development Organization of Iran and the Iran Power Plant Project Management Company (Mapna) and the participation of its foreign partner, namely Ansaldo Italy, as part of the 30 turbine project, the construction and the first unit of it on 4/16/1380 and the last The unit was put into operation on 29/9/2013. In the construction of the construction of the gas section of the power plant, internal contracting capacities at the level It has been widely used for the development of power plant construction technology.The gas turbines of this power plant are the V94.2 model made by the German Siemens company, which the Italian Ansaldo company sold to Iran under the license of the said company. Next, the steam section of the power plant, consisting of 4 units of 160 MW, was put into operation in 1986 and 1978.
General characteristics of the power plant:
The above power plant was built in the 20th kilometer of Kerman highway, Rafsanjan, in an area of 120 hectares, the gas part of which, as mentioned,
consists of 8 gas units and the steam part also has 4 units with a nominal capacity of 160 megawatts per unit. It started on 10/83 and the first unit
was put into operation on 12/28/86 and the last unit on 12/22/87.In total, with the full use of the facilities of the steam department, the nominal capacity of this power plant reached a figure of 1912 megawatts, and later by carrying out upgrading operations on the gas units and installing the media system on 8 gas units, the total capacity of the power plant increased to a figure of 2000 megawatts. In this sense, it is one of several large power plants in the country.
The main fuel of the power plant is natural gas, and the second fuel is diesel, which is transported to the power plant with the help of pipelines and stored and used in 20 million liter metal tanks and 60 million liter concrete tank. The cost of constructing the gas section of the power plant is about 300 million euros, and the cost of setting up the steam section is almost twice the mentioned amount.The amount of gas and diesel fuel consumption of the power plant per megawatt hour of electric energy production in the open cycle mode is equivalent to 330 cubic meters of gas and 330 liters of diesel, and in the combined cycle mode, it is an average of 223 cubic meters of gas or 223 liters of diesel.
Power station posts:
In order to transfer the generated energy in the power plant units, two power station substations have been built. The substation voltage level is 230 kV in the gas sector and 400 kV in the steam sector. The 230 kV substation of the power plant has 19 feeders (9 line feeders, 9 power plant feeders and 1 feeder coupling) and is of double busbar type. The 400 kV substation of the power plant also has 10 feeders, including 3 line feeders, 4 power plant feeders, 1 coupling feeder, and 2 feeders connected to the 230 kV substation.
What is the combined cycle?
As shown in the block diagram, each V94.2 gas turbine consists of two combustion chambers installed on both sides of the turbine. After entering them, the fuel (gas or diesel) is ignited by the operation of the sparking system and enters the combustion chamber area with the air that enters the compressor from the inlet filters and exits after being compressed, and burns, producing a gas with a temperature of about 1060 degrees Celsius. The gas enters the gas turbine and causes the turbine to rotate and, as a result, the generator shaft and generates electricity. The output product of the gas turbine is smoke with a temperature of about 550 degrees Celsius, which enters the atmosphere as heat losses through the chimney, and thus the gas turbine has an efficiency of about 33 percent in the best operating conditions. In other words, the other 67 percent is considered as heat losses and is inefficient. The idea of the combined cycle is actually to recycle the 67 percent. In this way, in the exhaust outlet section of each gas turbine, by installing controlled valves, the hot gas is directed to the boiler section, so that the water in it is converted into superheated steam (very hot and dry steam) with a temperature of about 530 degrees Celsius and is used together with the steam output from the second boiler for use in a steam turbine. In this way, in the boiler section, since the heat output from the gas turbine is used for heating, the overall efficiency is increased, reaching a figure equivalent to 47 percent. After working in the steam turbine, this steam drops in temperature and reaches a temperature of about 60 degrees. Here, too, in order to reuse it, the steam is cooled by the cooling system (in the Shahid Soleimani power plant with the help of powerful air fans) and converted into water. After performing intermediate purification operations, it enters the feed tank for reuse, to re-enter the boiler and convert into superheated steam. This cycle is called a combined cycle, and the Shahid Soleimani power plant is considered one of the largest power plants of this type in the country. The water required by this power plant is supplied through several wells drilled in the Chopar plain and is entered and stored in the power plant’s raw water pool with a capacity of 3,200 cubic meters through a pipeline, so that it can be used by the power plant’s boilers after purification operations. The nominal water supply capacity of the said wells is about 80 liters per second.
Technical and engineering capabilities:
- Supervision of overhaul of gas units 2
- Calibration of various instruments
- Start-up and commissioning of gas units 2
- Supervision of LTE repairs and upgrade plans
- Start-up and commissioning of steam units and recovery boilers
- Ability to manufacture a number of power plant components (domestic)
- Operation and commissioning of combined cycle units
- Operation and commissioning of power plant equipment and ancillary facilities
- Operation and commissioning of network equipment in an isolated manner
- Turbine troubleshooting2
- Ability to implement and consult on quality management systems and establish MIS management information systems
- Routine repairs of gas units 2 and combined cycle steam units
- Major repairs of gas units 2
- Providing technical and supervisory advice on gas units 2 and combined cycle units
- Providing advice on CM
- Start-up, commissioning and operation of high voltage substations (230-400)KV
- Also This company is ready to provide numerous services in the following fields: financial consulting, warehousing and accounting, recruitment and trade (logistics and clearance of goods)
- Providing educational services in technical and administrative fields
Key features of the Shahid Soleimani Power Plant in Kerman:
A) Automatic equipment of the power plant:
This power plant is one of the most modern and automatic power plants in the country with high efficiency and availability. Naturally, considering the above and the volume of automation equipment used, the relevant human resources must have acceptable expertise and experience in order to be able to use it in accordance with the needs of modern technologies.
B) Speed of connection to the network:
The gas turbines of this power plant can be started and connected to the network in cold conditions within a maximum of 5 minutes and in hot conditions within a maximum of one to three hours. This is important considering the characteristics of our country’s network and the potential needs that sometimes occur instantaneously, especially during peak electricity consumption hours.
c) Use of mixed fuel:
The use of mixed fuel is another indicator of the Kerman power plant, so that in the event of a shortage of any of the gas or diesel fuels, the deficit of the other fuel can be easily compensated by using a second fuel.
d) Control of environmental pollutants:
This power plant is one of the healthiest power plants in the world in terms of the subject under discussion. The use of a premix burner with a water flame combined with complete combustion reduces NOX and greenhouse gases and reduces environmental pollutants resulting from the above issue to their lowest level.
E) Use of flared boilers: Considering that the production rate of gas turbines depends on the ambient temperature and pressure, flared boilers have been used at the Kerman Power Plant to prevent a drop in steam unit production during the summer season. These flares are used at the appropriate time and prevent a drop in steam unit production.
Producing light in the heart of the desert
Those who have studied the history of the Iranian peoples of the distant past would have known how our ancestors lived in this ancient land and adapted to its deprivation and sometimes oppression in order to convey this ancient treasure to us without any reduction or reduction. The desert, which on the surface evokes fear and flight, is inwardly full of mystery, kindness and oppression, and you know and we know, what meaning and significance light has in the darkness.
Today, a group of workers in the country’s electricity industry, far from the facilities and blessings of the city and its blessings, in the dust of the scorching heat of the desert, are captivated by its tenderness and are lovingly engaged in producing light. The preservation of this sacred love is the optimal use and blinding of the flame of excess lamps. May they join hands in this worthy act so that the light in the heart of this thirsty desert remains eternal and never evokes fear and flight in the minds.